All projectsMaterial handling equipment · Project 05

Thrust reverser handling system

Handling gantry developed to support, move and position a thrust reverser, with precise control of interfaces, clamping and operator access.

DisciplineHandling · Lifting, travel & positioning
Documented scope8 project stages
Thrust reverser handling system — FORGIA industrial project
01 — Project journey

From requirement to industrial reality.

A documented view of the decisive engineering, manufacturing and validation steps.

  1. 01Engineering & 3D CAD
  2. 022D drawings & bill of materials
  3. 03Calculations & validation
  4. 04GPS tolerancing, tolerance stacks & fits
  5. 05Pneumatic diagrams & controls
  6. 06Manufacturing & assembly
  7. 07Load testing & validation
  8. 08Integration & commissioning
Stage 01

Engineering & 3D CAD

CATIA V6 · Overall architecture, guides, control mechanisms and operator access

Stage 02

2D drawings & bill of materials

Assembly drawings, layout, functional dimensions and component bill of materials (BOM)

Stage 03

Calculations & validation

Overall modelling, supporting-structure sizing and assembly verification

Stage 04

GPS tolerancing, tolerance stacks & fits

Tolerance-stack optimisation, geometric tolerancing and functional fit calculations

Stage 05

Pneumatic diagrams & controls

Definition of the clamping and release circuit, valves, connections and signalling devices

Stage 06

Manufacturing & assembly

Fabrication of the welded structure, component manufacturing and subassembly integration

Stage 07

Load testing & validation

Testing under representative load and validation of the structure and handling system behaviour

Stage 08

Integration & commissioning

Installation, mechanical and pneumatic integration, final adjustments and preparation for operation

Have a similar challenge?

Let’s study your
industrial project.

Request a quote